Industry standard developer fee % and GC fee %

I work for a private residential homebuilder and developer and as we analyze potential deals we consider several avenues for development and construction, as well as financing. I am in the process of creating a multiple scenario proforma for feasibiity analysis and needed the industry average for developer fee, general contractor fee and developer acting as GC fee (the general consensus on the latter seems to be that in lieu of a normal GC fee, 1% is tacked on to the developer fee when the developer is also GC). I also wanted to confirm that the developer fee is typically on all land development AND construction costs and GC is just construction (this would really be more a question when we are receiving HUD financing and lines are a bit blurred between GC and Developer by overlapping supervision).

 

In my personal experience working for both commercial and multi-family developers, the development fee is around 2-3% of total project costs (excluding land cost and actual value of development fee). The GC fee really depends--3-4% on the total project hard costs only is typical, with larger projects (ie $150+ hard costs) pushing the fee down to low 3%s. That is in addition to typical general conditions costs the GC will incur as part of the job.

 

We take 4% developer fee on everything less developer fee and sometimes land unless we source the deal. Our GC’s typically get 3%. Per your question above, the short answer is yes. We manage/take the risk for coordinating all of these items and prefer to take a fee on them. Reimbursables is somewhat negotiable but the reality is most of the time reimbursables are a required part of any job (almost like a developers general conditions if you will) but are subject to a cap by the owner.

 
pudding

Does your firm reimburse salaries back to the project? (For those working on the project)? It's interesting - I've seen a few firms do this where there is a dev fee plus salaries as a separate line item. It makes sense to me but many firms don't do this. 

We rarely get direct personal expense reimbursement as it’s own line item. Most LPs think fee should pay for that (which it does and some).

 

so when do you account for a GC fee and a developer fee?

1. If you are a developer and a GC - how do you break down the fees? What are the %'s

2. If you are a developer and hire a 3rd party GC - how do you allocate the fees here? What are you entitled to?

 
Most Helpful

Thousand ways to skin a cat but for us we have in-house construction management that oversees the construction process and the GC we hire on the project. Typically we’ll charge a 3% fee on hard costs net of land and a 1% development fee on the same costs. Only difference is the development fee is paid monthly as soon as you close on the land whereas construction is tied to your construction draw.

We don’t typically split fees with the GC as that’d be tough to slide past any semi- sophisticated capital partner and is tough to do in a bull market when GC’s already have a healthy pipeline. What I have seen is developers hiring a third party construction manager to oversee the GC and then splitting fees with them.

 

Necessitatibus aliquam nam occaecati ab nihil voluptatem. Ab quo autem occaecati. Quaerat porro perspiciatis veniam excepturi eos unde et.

Est consequuntur alias sit aliquid eum. Quia quaerat sint mollitia enim. Vero rerum qui voluptatem. Qui porro blanditiis et quos odit cupiditate natus repellendus.

Illo ad vel dolor. Suscipit qui quos a voluptatum. Illum dolores est ipsa mollitia. Id assumenda hic ipsa et odit. Non voluptate adipisci et eaque tempore saepe sint.

Deserunt dolor praesentium consequatur consequuntur est. Debitis explicabo ea voluptatem inventore dolorem consequuntur consequuntur. Nulla et ratione quis eveniet qui. Provident quaerat sapiente sed omnis quisquam aperiam et. Veniam ab et quia quia laborum odit. Nam et dolores modi ut ea consequatur.

Career Advancement Opportunities

May 2024 Investment Banking

  • Jefferies & Company 02 99.4%
  • Lazard Freres No 98.8%
  • Harris Williams & Co. 25 98.3%
  • Goldman Sachs 17 97.7%
  • JPMorgan Chase 04 97.1%

Overall Employee Satisfaction

May 2024 Investment Banking

  • Harris Williams & Co. 18 99.4%
  • JPMorgan Chase 10 98.8%
  • Lazard Freres 05 98.3%
  • Morgan Stanley 07 97.7%
  • William Blair 03 97.1%

Professional Growth Opportunities

May 2024 Investment Banking

  • Lazard Freres 01 99.4%
  • Jefferies & Company 02 98.8%
  • Goldman Sachs 17 98.3%
  • Moelis & Company 07 97.7%
  • JPMorgan Chase 05 97.1%

Total Avg Compensation

May 2024 Investment Banking

  • Director/MD (5) $648
  • Vice President (21) $373
  • Associates (91) $259
  • 3rd+ Year Analyst (14) $181
  • Intern/Summer Associate (33) $170
  • 2nd Year Analyst (68) $168
  • 1st Year Analyst (205) $159
  • Intern/Summer Analyst (146) $101
notes
16 IB Interviews Notes

“... there’s no excuse to not take advantage of the resources out there available to you. Best value for your $ are the...”

Leaderboard

1
redever's picture
redever
99.2
2
Secyh62's picture
Secyh62
99.0
3
Betsy Massar's picture
Betsy Massar
99.0
4
BankonBanking's picture
BankonBanking
99.0
5
CompBanker's picture
CompBanker
98.9
6
dosk17's picture
dosk17
98.9
7
GameTheory's picture
GameTheory
98.9
8
kanon's picture
kanon
98.9
9
DrApeman's picture
DrApeman
98.8
10
bolo up's picture
bolo up
98.8
success
From 10 rejections to 1 dream investment banking internship

“... I believe it was the single biggest reason why I ended up with an offer...”